Détail de l'actualité

TSMC Delays Production Start at Arizona Fab to 2025

21/07/2023

Chairman Mark Liu announced yesterday that TSMC has decided to postpone the start of production at its Arizona fab from 2024 to 2025. The delay is primarily due to a shortage of skilled technicians required for the semiconductor-grade facility.

Liu explained, "We are currently facing challenges due to a lack of skilled workers with the specific expertise needed for equipment installation in a semiconductor-grade facility. While we are actively addressing this issue, including temporarily assigning experienced technicians from Taiwan to train local skilled workers, we anticipate that the production schedule for N4 process technology will be extended to 2025.

Initially, Fab 21 was scheduled to begin production in early 2024 and was designed to operate at a capacity of 20k wafers per month.

Earlier reports suggested that TSMC was sending 500 employees from Taiwan to Arizona to assist in launching the fab. However, it appears that this workforce is proving to be insufficient. TSMC has also expressed concerns about the work ethic of American workers, stating that they do not work diligently enough.

TSMC is committed to addressing these challenges and ensuring the successful establishment of the Arizona fab, but the revised timeline reflects the need for additional skilled workers and training efforts.

TSMC

Mots clés

Nouvelles croisées

1. SR626SW Battery: Everything You Need to Know

SR626SW Battery: Everything You Need to Know

2. Global Semiconductor Capacity on the Rise in 2024

Global Semiconductor Capacity on the Rise in 2024

3. Cambridge-Based QPT Develops Groundbreaking GaN Au...

Cambridge-Based QPT Develops Groundbreaking GaN Automotive Traction Inverter

4. PC Market Saw a Significant Decline

PC Market Saw a Significant Decline

5. DL2032 vs CR2032: The Ultimate Battery Face-Off

DL2032 vs CR2032: The Ultimate Battery Face-Off

6. ADI has announced an investment of €630 million in...

ADI has announced an investment of €630 million in a new R&D

7. Introducing Arduino Uno R4: Evolution with 32-bit ...

Introducing Arduino Uno R4: Evolution with 32-bit Power

8. TSMC Record-Breaking July: A Revenue Milestone

TSMC Record-Breaking July: A Revenue Milestone

9. European Space Agency Partners with Redwire to Dev...

European Space Agency Partners with Redwire to Develop Robotic Arm Prototype for Argonaut Lunar Lander

10. AMD Continues Spartan 6 FPGA Supply Until 2030

AMD Continues Spartan 6 FPGA Supply Until 2030